Construction progress Cityquartier, Wiener Neustadt 26.09.2017
The floor slab and the cellar walls have already been completely erected.
In the area of the stairways 1, 2 and 3, the construction of the ground floor walls has now been completed. In the area of stairways 2 and 3 the production of the walls on the first floor is in full running and the stairfloor 3 was already started with the formwork of the ceiling above the first floor.
The finished parts for the element ceilings of the remaining areas around stairfloor 4 are continuously delivered to the construction site. For the sections where local concrete is used, the necessary formwork and reinforcement are produced.