In the northern section of the building, the concrete work is almost completed and the angled end of the building is clearly visible. The drywall has been installed in a number of flats and the windows have already been fitted. In the north-eastern section, at the corner of the station square, the pipes for the central heated flooring system have been installed and before Christmas, the screed will be poured in these 22 flats. In the southern section, the ceiling above the first floor and some walls on the second floor have been built and the ceiling above the parking ramp has also been concreted.