Gaadner Straße 21a+23, Hinterbrühl – Interior work picks up speed

The first few flats are starting to take shape at the project in Gaadner Strasse and the eventual rooms are already clearly recognisable. Now that the building site has been weatherproofed and the building roof has been sealed, it is now time to start the interior work. To start with, the visible reinforced concrete surfaces have been levelled. Following this, the plumbing has been installed in the shafts to each part of the building.

This means that additional pipework is now being installed in the residential properties. Most of the substructures for the drywall construction have already been installed and the unfinished ceilings in the bathrooms have now been waterproofed. All of the trades are working closely together to create the interior spaces bit by bit.