The plumbing and façade work is almost completed and the scaffolding will be gradually removed over the next few days so that the outdoor work can start.
Drainage, filter and distribution shafts were already delivered and will be installed very soon.
The concrete screed was applied in April and the tiling work started in June.
Most of the painting and electrical work in building section 1 has been completed and this work is now progressing rapidly in building section 2.