Gesundheitswelt Ost, Wr. Neustadt – The entire complex is taking shape

In the past few weeks, a lot has happened on the construction site. Seen from the outside, the entire complex with its individual sections is already taking shape. Since all the standard floors have now been built in construction phase 1, the structural work on the top floor has started. The first walls are already in place. At the same time, the windows on the ground floor and the first floor are being mounted. The work in construction phase 2 is also progressing. The ceiling above the third floor is being formed and reinforced. Meanwhile, the basic installation in the basement and the construction of the shafts on the first floor are in progress.

<<see project>>