The construction work progress on the facade is now clearly visible.
Work on the roofs is also progressing rapidly, with the recoolers and fans being installed and the final roof finishes in some areas.
Screed work has been completed in the rooms on the upper floors and cavity floors have been laid in the corridors and stairwells.
Many of the doors have been installed on the basement floors.