Part of the south facade has been completed. Work is progressing in parallel on all the other external facades. In many areas of the basement floors, the construction of suspended ceilings is well-advanced. The tiling work in the kitchen area of the cafeteria has been completed and the freezers have been installed. The first handrails have also been installed and rubber flooring has been laid in several classrooms.