Since the start of construction work in October, we are pleased to report that progress on the kindergarten in Franz-Huber-Gasse in Schwadorf is quite noticeable. The builder is currently concreting the ceiling and the terrace support above the added first floor. The walls on the first floor have already been completed. In the following week, the attic will be brick-built, and the second layer of concrete will be poured onto the ceiling. The black tiler will apply vapour insulation to the roof before the Christmas holidays and the start of the new year.
There is already work in progress in the existing building on the ground floor. The ceiling breakthrough leading through the existing ceiling into the windscreen for the installation of the lift has been completed. Plumbers, electricians, drywallers and fitters have already been working on the job. The lift shaft walls are currently being constructed with casing blocks.