Primary School Laaer Berg, Vienna – Soon completion of the building structure

Preparations are underway for the concreting of the slab above the second floor. As soon as this phase is completed, we will start to form the slope of the roof surfaces to ensure that the structural work can be completed as soon as possible.

The TGA building services contractors have already started work on the second basement level of the extension. Preparations are also underway in the basement of the existing building for the remodelling of the ventilation, water and electrical ducts required by the extension.