End of construction (phase 1) Parking deck Oberwart

End of construction (phase 1) Parking deck Oberwart 12.07.2019 The first phase of the parking deck was completed in cooperation with STRABAG AG as the general contractor. On behalf of Burgenländische Krankenanstalten GmbH, a total of 314 parking spaces were … Continued

Construction progress Parking deck Oberwart

Baufortschritt Parkdeck Oberwart

Construction progress Parking deck Oberwart 12.04.2019 All steel beams, light purlins and trapezoidal sheets were installed, so the roof is now completed. Now that the concrete has already been laid, it will soon be possible to start coating the surfaces … Continued

Construction progress Parking deck Oberwart

Baufortschritt Cityquartier, Wiener Neustadt

Construction progress Parking deck Oberwart 23.01.2019 The first phase of the structural work is complete! The dismantling of the construction crane has already started. All installed supports, prefabricated balustrades, hollow planks and hollow walls form the completed shell of the … Continued

Parking deck Oberwart

Project information

Procedure
Competition
Client
Burgenländische Krankenanstalten GmbH
Josef Hyrtl-Platz 4
7000 Eisenstadt
Principal
STRABAG AG, Direktion AS-Hochbau, Bereich NÖ-Süd, Burgenland
Schleppbahngasse 8
2700 Wiener Neustadt
Address
Dornburggasse, 7400 Oberwart
Start of planning
10/2017
Start of construction works
10/2018
Completion
07/2019
Construction costs
approx. 5.50 Mio. (net)
Size of order
General planning

Directly opposite the main entrance of the new Oberwarter Hospital, the garage building forms an urbanistic vis-a-vis. When approached from the ring road, it serves as the head structure of the adjoining industrial estate. The parking deck and the free parking spaces are located in such a way that the distances to the main entrance of the hospital are as short as possible. The access roads at the northern corner of the property have generous back dust areas. By separating the access systems, it is possible to train car traffic and footpaths on the property without crossing them.

The parking deck is configured with four levels in such a way that even the lowest level can be designed as an open parking deck, as it is opened as far as possible on the long side of the road via embankments, thus ensuring the required flow through. The gentle slope of the site or the embankment on Dornburggasse is used by the split-level system for the most efficient development possible. Thanks to the column-free tramlines, the wide-span precast construction offers a future-proof system: efficient, flexible, low-maintenance and user-friendly. A designed facade of curtain-type aluminum profiles will be erected on the front side opposite the hospital. The roofing of the top floor can be equipped with solar modules if required.

The garage will be built in two construction phases, whereby the first construction phase will remain almost unrestrictedly in operation during the construction period. A total of 314 parking spaces inside the parking garage as well as a total of 145 outside parking spaces were built in the first construction phase. The second construction phase represents a generous extension of the parking deck and offers an additional approx. 360 parking spaces and approx. 20 free parking spaces. The cubature’s of both structures are almost identical, but the structure of phase 1 is turned by 90° compared to phase 2.