End of construction Stadlbreiten 9+11

Stadlbreiten 9+11

End of construction Stadlbreiten 9+11 24.04.2019 The new residential complex was finished in cooperation with STRABAG AG as the general contractor for the at home Immobilien-GmbH and handed over to the tenants. A total of 46 apartments, divided into 3 … Continued

Construction progress Stadlbreiten 9+11

Baufortschritt Stadlbreiten 9+11

Construction progress Stadlbreiten 9+11 14.03.2019 The construction work is coming to an end. The facades and exterior railings are finished. In staircase 3, all the wall and floor coverings in the apartments were already manufactured and most of the interior … Continued

Construction progress Stadlbreiten 9+11

Baufortschritt Stadlbreiten 9+11

Construction progress Stadlbreiten 9+11 29.11.2018 The construction work is progressing at full speed. The facades of stairs 2 and 3 are already completely finished and the framework is almost dismantled. The plumbing work in the attic and roof areas is … Continued

Stadlbreiten 9+11, Vienna

Project information

Procedure
Selection procedure
Client
at Home Immobilien-GmbH
Hernalser Gürtel 1
1170 Vienna
Principal
STRABAG AG Hoch- und Ingenieurbau UB 3 C, Direktion AR
Donau-City-Str. 9
1220 Vienna
Address
Stadlbreiten 9+11, 1220 Vienna
Start of planning
03/2014
Start of construction works
10/2017
Completion
04/2019
Construction costs
3,90 Mio. (net)
Size of order
General planning

Videos

The building project Stadlbreiten is located in the 22nd Viennese municipal district and expands development on the outskirts with three structures, which are arranged orthogonally to the property boundary and form a continuous facade to the east. The residential building opens to the west with two inner courtyards. Dormers on the longitudinal side of the building optically divide it into smaller parts by breaking the line of the roof slope. The regularity of the facade is slackened by mutually shifted balconies. Brown coloured-ribbons between the windows additionally structure the facade. The property is accessed on the one hand via Stadlbreiten Street and on the other hand via a footpath on the northern property boundary. From the street side there is a barrier-free footpath to the staircases of all buildings, each of which is equipped with an elevator. In total 46 flats with two to four rooms and an underground parking were erected. All apartments are planned throughout with one storey, the compact room arrangement with minimized access floor area is complemented by outdoor areas. Ground floor flats possess a garden for their own disposal, flats above ground are provided with either balconies or roof decks.