Step by step, the work in Saltenstrasse 1 is coming to an end:
Inside the building, the tiling work is progressing continuously, apartment by apartment. At the same time, the installation of the parquet flooring has started starting from staircase 2. After that, the works for the completion of the sanitary and electrical installations have already started. There is also a lot of activity around the whole building. While the last balcony slabs are still being fitted upstairs, the pavements, the terraces, and now also the lawn have already been prepared in the garden. Next, the assembly of the doors and the final finishing work will start before the cleaning can start.