The screed work in the standard and attic floors has been completed and the tiles in the bathrooms, toilets and kitchenettes on the 1st floors have already been laid. The drywall work is also almost finished – with the exception of the last attic floors. The façade insulation has been glued on the street side and the filling work has already started. The show flat is in progress and the parquet flooring has just been laid. More than half of the tinsmith work on the roof has been completed and the installation of the interior railings is already in full swing.