The progress of the construction work at Schrottensteingasse 6 over the past few months is very visible on the facades.
On some views of the apartment complex, the rubbing down of the thermal insulation composite system has been completed successfully.
The scaffolding has also been completely removed in these areas.
The railings in the communal outdoor areas have also been largely installed, allowing the flooring and lighting to be installed for the future use of these areas.
Inside, the necessary insulation has been applied to the unfinished floors in most of the apartments and the underfloor heating pipes have been laid.
On some floors, the finished heated screed and closed drywalls are already visible, allowing the final layouts of the units to be clearly seen and the future living spaces to be easily imagined.