At the construction site in Schrottensteingasse, the excavation has now been completed and the sheet piling has already started in some areas.
The pit for the double parking spaces on the eastern boundary of the site has now been concreted already and work has started on the granular subbases on the northern boundary of the site.
The first reinforcement bars for the floor slab will be laid in the next few days.