End of construction Weinzingergasse

As planned, the facility was successfully finished after 18 months of construction time and could be handed over to the client from where it was handed over to the tenants. The individually contracted contractors cooperated with each other in a … Continued

Construction progress Weinzingergasse

Construction progress Weinzingergasse 19.12.2019 In front of the house, the asphalt work was finished and the construction site equipment was removed so that the pavement can now be freely used again. In the interior, the tiling work is finished and … Continued

Construction progress Weinzingergasse

Construction progress Weinzingergasse 22.11.2019 In a shining white, plaster facade appears after the scaffolding has been dismantled. This completes the building exterior of the upper floors. Accordingly, the construction work on the exterior facilities has now been started and the … Continued

Weinzingergasse 5, Vienna

Project information

Procedure
Selection procedure
Client
Private
Principal
Private
Address
Weinzingergasse 5, 1190 Vienna
Start of planning
06/2016
Start of construction works
08/2018
Completion
02/2020
Construction costs
-
Size of order
General planning and construction supervision

Videos

In the 19th district of Vienna, this newly built and well-equipped residential building offers a selection of seven 3-, 4- and 5-room apartments. On the street side, the building blends in with its elegantly structured façade as a modern feature in the enclosed development of the historical location. On the garden side, all residential premises open up to private open spaces. The floor-to-ceiling glazing allows a generous view of the greenery and provides a sun-flooded interior. The central location of the property, with the nearby Sonnbergmarkt, the Strauß-Lanner-Park, and the connection to the Wienerwald, offers further recreational and sports activities, which are some of the benefits of this high-quality Viennese neighborhood.